Cambio de Cojinete en Generador Eléctrico para Disminución de Uso…

<% join_label %>

Cambio de Cojinete en Generador Eléctrico para Disminución de Uso de Agua de Enfriamiento Orazul Energy

Show Full Map
Amazon
Area: 5888268 km2
Countries:
Brazil; Peru; Suriname; France; Colombia; Guyana; Bolivia; Venezuela; Ecuador
Cities:
Santa Cruz; Manaus; La Paz
PFAF ID:
HydroBasin Level:
Baseline Water Stress:
Water Quality Stress:
Sanitation Access Stress:
Click to view individual basin.
Location
Click Icon to Show on Map
City & Country
,
()

Quick Info

Countries: Peru
Regions: Amazonas
Project SDGs:
Includes Sustainable Development Goals from the project and its locations.
Increase Access to Water, Sanitation, Hygiene (SDG 6.1 & 6.2)
Water Use Efficiency (SDG 6.4)
Project Tags:
Includes tags from the project and its locations.
Safe, Affordable Water
Progress to Date: 0 NA
Services Needed: No services needed/offered
Desired Partner: Other
Language: Español
Start & End Dates: Dec. 31, 2014  »  Jun. 01, 2015
Project Source: El Agua nos Une
Profile Completion: 64%

Project Overview

La Central Termoeléctrica de Aguaytía de la empresa Orazul Energy cuenta con dos turbinas a gas (modelo GT11NMC XL/LP) de 88.441 MW y 86.964 MW que tras la actualización y mejora de los compresores de las turbo-gas, se logró el incremento de su capacidad de generación de energía en 9 MW en cada una. Al hacer este incremento, se observó que la temperatura del metal del cojinete N°3 había aumentado también. Ello provocó que se utilice un sistema de enfriamiento al 100% de su c…

Read More

La Central Termoeléctrica de Aguaytía de la empresa Orazul Energy cuenta con dos turbinas a gas (modelo GT11NMC XL/LP) de 88.441 MW y 86.964 MW que tras la actualización y mejora de los compresores de las turbo-gas, se logró el incremento de su capacidad de generación de energía en 9 MW en cada una. Al hacer este incremento, se observó que la temperatura del metal del cojinete N°3 había aumentado también. Ello provocó que se utilice un sistema de enfriamiento al 100% de su capacidad disponible, con 3 ventiladores asociados al sistema. Sin embargo, durante la temporada de calor en la que las temperaturas ambientales exceden los 30°C, el sistema llegó a niveles no aceptables de temperatura en el cojinete, alcanzando con mayor frecuencia valores mayores a 100 °C lo que obligó a implementar un sistema auxiliar de enfriamiento con agua. Se analizaron alternativas para el cambio de cojinetes afectados por un diseño mejorado. De este modo Orazul Energy invirtió en el cambio de diseño del cojinete N°3, lo cual permitió mantener temperaturas menores del metal, siendo la utilización de agua innecesaria para el enfriamiento.

Project Results

Reducción de 900 m3/año de uso de agua

Ahorro de 1,759.09 USD/año por pago de tarifa de uso de agua industrial

Sourced From:

Latest updates

No current notifications are found for the projects, organizations, and other topics you are currently following.

Following

Partner Organizations


None found.

Alejandro Conza
Primary Contact  
Maly Puerto
Admin  

Discussion

No comments found - be the first to add yours below!

No comments found. Log in and add yours below!

Log in to add your comment!


   Loading Matches

No lessons found.

Os projetos de Captação de Água Pluvial da Rede Engenheiros sem Fronteiras encontram sua maior dificuldade na aquisição do material para construção dos módulos. Uma vez que somos uma Organização Social e não temos lucro, precisamos buscar outros meios de …

Millions of people globally do not have ready access to running water at their homes. They are forced to walk 6 – 10 miles carrying heavy (47 lb. – 21Kgs) water containers daily. The cost of having water delivered is …

If my our team 26-27 years time consuming financial losses &amp; expenses further future financial free dom heavy cimpensation fullfill immediately first than all mejority established stallwarts related water &amp; corruption nexus activities keep sluggish without speaking dormant because they …

It is very important for us because the one soap for one child project needs a lot of water during production of soap. So we have now clear knowledge on how to save water during post and pre-production.

Water-related Action Plans should be based on SDG 6 monitoring and designed with the participation of all relevant stakeholders, to serve as a collective roadmap for different sectors to contribute to achieving the SDGs. Equitable and inclusive water resources management …

OXIDATION PONDS Oxidation ponds were developed during times when the populations were not as great as we are experiencing today. Water quality requirements have been strictly increased for compliance for release. Today the water compliance is close to a class …

This is an excerpt of the 1st of 4 findings in the 2021 WASH4Work Insights Report: Raising Our Ambition to Wash Resilience: Unlocking The Co-Benefits Of Water, Sanitation, and Hygiene In Corporate Water Stewardship This excerpt breaks down some of …

This is a small excerpt from the COP 27 Business Declaration For Climate Resilient Water, Sanitation &amp; Hygiene (WASH) which gives the case for business action on WASH, demonstrates the leadership and commitment of the corporate water stewardship community to …

You have to SHOW UP! Going to a River cleanup will make you see life differently, when you see all the waste that washes up on the river banks and gets caught in trees and root systems, it causes you …